75 Day Work Plan

In October, Brighton City Manager Philip Rodriguez recently rolled out a 75-day work plan in order to address the city’s top pressing issues with the goal of providing clarity, transparency and accountability to our community. The plan addresses a number of specific actions that Rodriguez and city staff will undertake between now and Dec. 31.

“The goals and objectives listed in the plan will require a significant amount of time and energy for staff and it will be one of our top work priorities for the remainder of the year,” Rodriguez said. “I am confident that focusing on these items will create positive outcomes for the organization and the community, including prioritizing our customers, streamlining services to increase efficiencies, better aligning of our organization plan, and increasing support needed in certain areas throughout the city.”

Check on this page often to stay connected with our progress on this plan.

Watch the video below to hear about the plan from City Manager Rodriguez. 

City's 75 Day Work Plan

Brighton City Manager Philip Rodriguez recently rolled out a 75-day work plan in order to address the city’s top pressing issues with the goal of providing clarity, transparency and accountability to our community. The plan addresses a number of specific actions that Rodriguez and city staff will undertake between now and Dec. 31.

Posted by City of Brighton, Colorado Government on Thursday, October 25, 2018

Goals & Objectives:

OCT 18 – DEC 31

Transform Billing Cycles

_____


Prioritize Customers

_____


Utility Billing Moved to Finance

_____


Review and Rebuild Utility Rates

_____


New City Auditors

_____


Council & Community Involvement

_____


New Key Positions Focused on the Plan

_____

Overall 75 Day Work Plan Update 2
75 Day Plan 2
  • Objective 1.1 update: Projected completion November 2018, pending City Council action
75 Day Plan 3
  • Objective 1.2 update: Projected completion December 2018, 3rd party review underway
75 Day Plan 4
  • Objective 1.3 update: Projected completion January 2019, pending City Council action
Objective 1.4 75 Day Work Plan Update 2
  • Objective 1.4 update: Projected completion January 2019, solicitation underway
75 Day Plan 6
  • Objective 1.5 update: Projected completion December 2018, pending City Council action
Objective 1.6 75 Day Work Plan Update 2
  • Objective 1.6 update: Projected completion November 2018, pending City Council action
Objective 1.7 75 Day Plan Update 2
  • Objective 1.7 update: Projected completion December 2018, RFP issued 10/22/18.
75 Day Plan 9
75 Day Plan 10
  • Objective 1.9 update: Projected completion December 2018, process underway
75 Day Plan 11
Objective 1.11 75 Day Work Plan Update 2
  • Objective 1.11 update: Projected completion December 2018, pending City Council action
Objective 1.12 75 Day Plan Update 2